Core Strategy Consultation on Strategy Directions 2008

Representation ID: 19812

Received: 30/01/2009

Respondent: East Sussex County Council

Representation Summary:

Whilst the 'plan B' options do not detract from the necessity of the introduction of the BHLR, the preferred strategy does take account of the eventuality of the BHLR either slipping in timescale or not being built.


The timing for the completion of the BHLR is incorrect in the various references throughout the document which should be amended to reflect and align with dates referenced within the BHLR Major Scheme Business Case and supportive documentation. The current anticipated completion date is December 2012. (It is noted that the table found in 13.9 also gives a completion date of 2103)