Q2. Do you agree that there is clear infrastructure funding gap?
Representation ID: 21725
Received: 25/09/2014
Respondent: Gladman Developments
Local planning authorities need to be able to demonstrate the infrastructure need and funding gap and ensure the level of total CIL receipts that could be generated through the levy reflects needs.
When establishing a funding gap, it is vital to take account of every possible income stream. The Council need to have an up-to-date, robust evidence base that justifies the infrastructure based on propsed development.
The Council needs to ensure that they have a full understanding of infrastructure costs to meet the needs. Gladman believe that it is inappropriate to set the levy based on a partial understanding.
Introduction
Gladman Developments has considerable experience in the development industry in a number of sectors including residential and employment land. Gladman are aware that Rother Council have a Local Plan which has recently been found sound (subject to modifications) and that alongside this the Council are in the process of preparing a Community Infrastructure Levy for the area. This Consultation is for the PDCS stage of the CIL.
CIL is intended to have a positive effect on development. The latest CLG guidance notes that "The levy is expected to have a positive economic effect on development across a local plan area. When deciding the levy rates, an appropriate balance must be struck between additional investment for infrastructure to support development and the potential economic effect on the viability of developments...This balance is at the centre of the charge setting process" (Section 2.2, CLG Guidance, 2014).
In accordance with the latest CIL Regulations, the Council is required to strike an appropriate balance between the desirability of funding from CIL and the potential effects (taken as a whole) of the imposition of CIL on the economic viability of development across the local authority area. The Council must consider the impact of CIL together with the policies contained in the Local Plan on
developments within the borough when deciding an appropriate CIL rate.
Setting the levy at the appropriate rate will be key to ensuring that development comes forward in your local authority area and subsequently that the Local Plan is implemented. These representations address some key areas that local planning authorities must consider when preparing their CIL charging schedule, drawing on recent guidance produced by the CLG.
Funding gap / evidence base
Local planning authorities need to be able to demonstrate the infrastructure need and subsequent funding gap and must ensure that the level of total CIL receipts that could be generated through the levy reflects these true needs and the proposals in the Local Plan. The CIL should not be used by Council's as a mechanism for creating an unrealistic 'wish list' of infrastructure projects in their area.
When establishing a funding gap that CIL receipts are intended to contribute towards filling, it is vital that the Council take account of every possible income stream. This has to include an accurate assessment of future New Homes Bonus and council tax and business rates receipts generated as a result of new developments allocated in the Local Plan, as well as central government funding streams. This should also include an assessment of statutory undertakers' asset management plans, as these companies will at some stage be upgrading their systems/facilities. This also needs to be taken account of when assessing the infrastructure requirements of the authority.
The Council need to have an up to date, robust evidence base that fully justifies the infrastructure needs based on the amount of development that is required. Information on these infrastructure needs should, wherever possible, be drawn directly from the infrastructure planning that underpins the Development Plan, as this should identify the quantum and type of infrastructure required to realise their local development needs. If the authority's infrastructure planning is weak or out of date then the Council should undertake an exercise to refresh this. If the evidence base is not complete, robust and up to date the charging schedule will be unsound and the local planning authority will have difficulty adequately demonstrating their funding gap and subsequent CIL requirements.
The CLG guidance notes that: "Charging authorities should be able to show and
explain how their proposed Community Infrastructure Levy rate or rates will contribute towards the implementation of the relevant Plan, and support development across their area. Charging authorities will need to summarise their economic viability evidence. This evidence should be presented in a document (separate from the charging schedule) that shows the potential effects of the proposed levy rate or rates on the economic viability of development across the authority area" (Section 2:2:2:3, CLG Guidance, 2014).
It is important that in calculating the level of infrastructure the authority needs as a result of development the Council distinguishes between new and existing demands. New houses do not always create new pressure on infrastructure as evidence shows that a large proportion will be occupied by people already living in the borough, attending local schools, and registered with local GP surgeries. They will therefore require less infrastructure provision compared to new residents in the borough.
The available guidance makes it clear that CIL is expected to have a positive economic effect on development across an area in the medium to long term. As outlined in recent Inspector's Letters to East Devon District Council (April 2014), the CIL charging rates should not be set at such a level that would threaten development, and must be based on robust evidence and assumptions. The rate will also need to be appropriate over time, bearing in mind land values, market conditions and the wider economic climate change rapidly. The viability impact of incremental policy obligations, such as stepped Code for Sustainable Homes targets, must be assessed and reflected in the charging schedule.
The Council needs to ensure that they have a full understanding of the potential costs of infrastructure projects needed to meet the infrastructure needs. Gladman believe that it is inappropriate to set the levy based on a partial understanding of these infrastructure costs and in particular if the total money needed for infrastructure is unknown.
Differential charging rates
The CLG guidance notes that the use of differential charging rates can be an appropriate approach where there is clear viability evidence to justify this. The CIL regulations allow charging authorities to apply differential rates in a flexible way, to help ensure the viability of development is not put at risk.
The rules around the use of differential rates in the Charging Schedule are clear: they can only be applied in relation to different geographical zones in which development would be situated, related to different types of development, and/or scales of development. Furthermore as the Government's CIL guidance and inspectors have made clear, differential rates should be set "based on economic viability considerations alone, rather than any planning or any other public policy related choices" (Paragraph 14, Newark and Sherwood EIP report, August 2011), and "CIL is not intended to be a planning policy tool" (Paragraph 23, Huntingdonshire EIP report, April 2012). Charging schedules with differential rates should not have a disproportionate impact on particular sectors or specialist forms of development.
It is integral when setting differential rates for different geographical areas that these differential rates are based on accurate, up to date housing market intelligence forming the evidence base for this decision.
Discretionary Relief
Regulation 55 of the CIL Regulations allows local authorities to grant relief for exceptional circumstances from liability to pay CIL. Such provision should be factored into the Council's CIL and will avoid rendering sites with specific and exceptional cost burdens unviable should exceptional circumstances arise.
Payments in Kind
Regulations 73 and 73A of the CIL Regulations provides a mechanism for local authorities to accept infrastructure payments, or payments in kind, for land or infrastructure to be provided instead of money to satisfy a charge arising the levy. An allowance for infrastructure payments should therefore be made available by the Council, recognising that there may be time, cost and efficiency benefits in accepting land or infrastructure from parties liable for payment of the levy.
Requirement to consult
As with Local Plans, local planning authorities have an obligation to consult at various stages of the CIL preparation process. However, the guidance does not provide details as to the format that this consultation must take or length of the consultation period. Gladman echo the CIL guidance and would urge your local authority to engage with local developers and others in the property industry early and throughout the process. This will help your authority to gain opinions from the market to feed into the preparatory work.
Once the charging schedule is ready for Examination the local authority must publish the draft schedule for a further stage of formal public consultation. In accordance with the CIL Guidance this must be for a period of at least four weeks, although it is considered good practice to allow at least six weeks, and longer if the issues under consideration are particularly complex.
Examination
As outlined in Section 2:2:5:1 of the 2014 CLG guidance the charging authority must appoint the examiner. The examiner must be independent and have the appropriate qualifications and experience. The guidance confirms that a Planning Inspector would fulfil these criteria.
Conformity with the National Planning Policy Framework (NPPF)
The NPPF provides the current central government planning policy and requirements for local planning authorities to meet. The NPPF places emphasis on sustainable development and in particular ensuring that the objectively assessed needs of an area are met through the requirements and policies within the new Local Plan.
It is fundamental that the Council ensures that the proposed levy rates are realistic and not set too high. Arbitrarily high rates may jeopardise the delivery of housing schemes within the area. This would be contrary to the Government's aim outlined in the Framework to "significantly boost the supply of housing", as schemes may not come forward due to viability issues.
The Council's CIL charging rates must not threaten the overall delivery of the Local Plan, by making sites unviable. This point is reiterated in the CLG guidance, which states that "Charging authorities should set a rate which does not threaten the ability to develop viably the sites and scale of development identified in the relevant Plan" (Section 2:2, CLG Guidance, 2014).When testing the impact of CIL it is vital that the assumptions that underlie the standard residual valuation approach used to test the impact on viability of CIL are realistic and accurate.
This should include abnormal costs, contingency costs, preliminary costs, and developer profit, which should reflect the current level of risk perceived in the market.
Gladman would urge the Council to adopt an instalments policy for CIL payments as this will give developers the flexibility to pay contributions in line with development phasing schemes and will facilitate cash flow and therefore development viability. With this in mind, in accordance with Regulation 8(3A) of the CIL Regulations the Council should also accept the phasing of planning permissions, with each phase treated as a separate chargeable development.
Gladman also remind the Council of the need to review CIL tariffs once these have been set. The economic climate will inevitably change over the course of the plan period and as such the levy rates that can be set whilst ensuring development remains viable will also change. In accordance with the CLG guidance "Charging authorities must keep their charging schedules under review and should ensure that levy charges remain appropriate over time. For example charging schedules should take account of changes in market conditions, and remain relevant to the funding gap for the infrastructure needed to support the development of the area" (Section 2:2:6:3, CLG Guidance, 2014).
Gladman believe that the Council need to have a clear understanding of the level of residential development to be brought forward in the plan period when preparing the charging schedule as this will directly influence the scale of CIL that will be generated. Without this the charging schedule will not reflect the relevant and true infrastructure needs of the area.
Comment
Community Infrastructure Levy (CIL) Preliminary Draft Charging Schedule and Regulation 123 List
Q3. Do you agree with the proposed residential CIL charging zones?
Representation ID: 21726
Received: 25/09/2014
Respondent: Gladman Developments
The CLG guidance notes that the use of differential rates can be an appropriate approach where evidence is clear. The regulations allow the application of differential rates, to ensure viability.
The rules are clear: they can only be applied in relation to different geographical zones in which development would be situated, related to different types of development, and/or scales of development. Charging schedules with differential rates should not have a disproportionate impact on particular sectors/specialist forms of development.
It is integral when setting differential rates for different areas that these rates are based on accurate, up-to-date housing market intelligence.
Introduction
Gladman Developments has considerable experience in the development industry in a number of sectors including residential and employment land. Gladman are aware that Rother Council have a Local Plan which has recently been found sound (subject to modifications) and that alongside this the Council are in the process of preparing a Community Infrastructure Levy for the area. This Consultation is for the PDCS stage of the CIL.
CIL is intended to have a positive effect on development. The latest CLG guidance notes that "The levy is expected to have a positive economic effect on development across a local plan area. When deciding the levy rates, an appropriate balance must be struck between additional investment for infrastructure to support development and the potential economic effect on the viability of developments...This balance is at the centre of the charge setting process" (Section 2.2, CLG Guidance, 2014).
In accordance with the latest CIL Regulations, the Council is required to strike an appropriate balance between the desirability of funding from CIL and the potential effects (taken as a whole) of the imposition of CIL on the economic viability of development across the local authority area. The Council must consider the impact of CIL together with the policies contained in the Local Plan on
developments within the borough when deciding an appropriate CIL rate.
Setting the levy at the appropriate rate will be key to ensuring that development comes forward in your local authority area and subsequently that the Local Plan is implemented. These representations address some key areas that local planning authorities must consider when preparing their CIL charging schedule, drawing on recent guidance produced by the CLG.
Funding gap / evidence base
Local planning authorities need to be able to demonstrate the infrastructure need and subsequent funding gap and must ensure that the level of total CIL receipts that could be generated through the levy reflects these true needs and the proposals in the Local Plan. The CIL should not be used by Council's as a mechanism for creating an unrealistic 'wish list' of infrastructure projects in their area.
When establishing a funding gap that CIL receipts are intended to contribute towards filling, it is vital that the Council take account of every possible income stream. This has to include an accurate assessment of future New Homes Bonus and council tax and business rates receipts generated as a result of new developments allocated in the Local Plan, as well as central government funding streams. This should also include an assessment of statutory undertakers' asset management plans, as these companies will at some stage be upgrading their systems/facilities. This also needs to be taken account of when assessing the infrastructure requirements of the authority.
The Council need to have an up to date, robust evidence base that fully justifies the infrastructure needs based on the amount of development that is required. Information on these infrastructure needs should, wherever possible, be drawn directly from the infrastructure planning that underpins the Development Plan, as this should identify the quantum and type of infrastructure required to realise their local development needs. If the authority's infrastructure planning is weak or out of date then the Council should undertake an exercise to refresh this. If the evidence base is not complete, robust and up to date the charging schedule will be unsound and the local planning authority will have difficulty adequately demonstrating their funding gap and subsequent CIL requirements.
The CLG guidance notes that: "Charging authorities should be able to show and
explain how their proposed Community Infrastructure Levy rate or rates will contribute towards the implementation of the relevant Plan, and support development across their area. Charging authorities will need to summarise their economic viability evidence. This evidence should be presented in a document (separate from the charging schedule) that shows the potential effects of the proposed levy rate or rates on the economic viability of development across the authority area" (Section 2:2:2:3, CLG Guidance, 2014).
It is important that in calculating the level of infrastructure the authority needs as a result of development the Council distinguishes between new and existing demands. New houses do not always create new pressure on infrastructure as evidence shows that a large proportion will be occupied by people already living in the borough, attending local schools, and registered with local GP surgeries. They will therefore require less infrastructure provision compared to new residents in the borough.
The available guidance makes it clear that CIL is expected to have a positive economic effect on development across an area in the medium to long term. As outlined in recent Inspector's Letters to East Devon District Council (April 2014), the CIL charging rates should not be set at such a level that would threaten development, and must be based on robust evidence and assumptions. The rate will also need to be appropriate over time, bearing in mind land values, market conditions and the wider economic climate change rapidly. The viability impact of incremental policy obligations, such as stepped Code for Sustainable Homes targets, must be assessed and reflected in the charging schedule.
The Council needs to ensure that they have a full understanding of the potential costs of infrastructure projects needed to meet the infrastructure needs. Gladman believe that it is inappropriate to set the levy based on a partial understanding of these infrastructure costs and in particular if the total money needed for infrastructure is unknown.
Differential charging rates
The CLG guidance notes that the use of differential charging rates can be an appropriate approach where there is clear viability evidence to justify this. The CIL regulations allow charging authorities to apply differential rates in a flexible way, to help ensure the viability of development is not put at risk.
The rules around the use of differential rates in the Charging Schedule are clear: they can only be applied in relation to different geographical zones in which development would be situated, related to different types of development, and/or scales of development. Furthermore as the Government's CIL guidance and inspectors have made clear, differential rates should be set "based on economic viability considerations alone, rather than any planning or any other public policy related choices" (Paragraph 14, Newark and Sherwood EIP report, August 2011), and "CIL is not intended to be a planning policy tool" (Paragraph 23, Huntingdonshire EIP report, April 2012). Charging schedules with differential rates should not have a disproportionate impact on particular sectors or specialist forms of development.
It is integral when setting differential rates for different geographical areas that these differential rates are based on accurate, up to date housing market intelligence forming the evidence base for this decision.
Discretionary Relief
Regulation 55 of the CIL Regulations allows local authorities to grant relief for exceptional circumstances from liability to pay CIL. Such provision should be factored into the Council's CIL and will avoid rendering sites with specific and exceptional cost burdens unviable should exceptional circumstances arise.
Payments in Kind
Regulations 73 and 73A of the CIL Regulations provides a mechanism for local authorities to accept infrastructure payments, or payments in kind, for land or infrastructure to be provided instead of money to satisfy a charge arising the levy. An allowance for infrastructure payments should therefore be made available by the Council, recognising that there may be time, cost and efficiency benefits in accepting land or infrastructure from parties liable for payment of the levy.
Requirement to consult
As with Local Plans, local planning authorities have an obligation to consult at various stages of the CIL preparation process. However, the guidance does not provide details as to the format that this consultation must take or length of the consultation period. Gladman echo the CIL guidance and would urge your local authority to engage with local developers and others in the property industry early and throughout the process. This will help your authority to gain opinions from the market to feed into the preparatory work.
Once the charging schedule is ready for Examination the local authority must publish the draft schedule for a further stage of formal public consultation. In accordance with the CIL Guidance this must be for a period of at least four weeks, although it is considered good practice to allow at least six weeks, and longer if the issues under consideration are particularly complex.
Examination
As outlined in Section 2:2:5:1 of the 2014 CLG guidance the charging authority must appoint the examiner. The examiner must be independent and have the appropriate qualifications and experience. The guidance confirms that a Planning Inspector would fulfil these criteria.
Conformity with the National Planning Policy Framework (NPPF)
The NPPF provides the current central government planning policy and requirements for local planning authorities to meet. The NPPF places emphasis on sustainable development and in particular ensuring that the objectively assessed needs of an area are met through the requirements and policies within the new Local Plan.
It is fundamental that the Council ensures that the proposed levy rates are realistic and not set too high. Arbitrarily high rates may jeopardise the delivery of housing schemes within the area. This would be contrary to the Government's aim outlined in the Framework to "significantly boost the supply of housing", as schemes may not come forward due to viability issues.
The Council's CIL charging rates must not threaten the overall delivery of the Local Plan, by making sites unviable. This point is reiterated in the CLG guidance, which states that "Charging authorities should set a rate which does not threaten the ability to develop viably the sites and scale of development identified in the relevant Plan" (Section 2:2, CLG Guidance, 2014).When testing the impact of CIL it is vital that the assumptions that underlie the standard residual valuation approach used to test the impact on viability of CIL are realistic and accurate.
This should include abnormal costs, contingency costs, preliminary costs, and developer profit, which should reflect the current level of risk perceived in the market.
Gladman would urge the Council to adopt an instalments policy for CIL payments as this will give developers the flexibility to pay contributions in line with development phasing schemes and will facilitate cash flow and therefore development viability. With this in mind, in accordance with Regulation 8(3A) of the CIL Regulations the Council should also accept the phasing of planning permissions, with each phase treated as a separate chargeable development.
Gladman also remind the Council of the need to review CIL tariffs once these have been set. The economic climate will inevitably change over the course of the plan period and as such the levy rates that can be set whilst ensuring development remains viable will also change. In accordance with the CLG guidance "Charging authorities must keep their charging schedules under review and should ensure that levy charges remain appropriate over time. For example charging schedules should take account of changes in market conditions, and remain relevant to the funding gap for the infrastructure needed to support the development of the area" (Section 2:2:6:3, CLG Guidance, 2014).
Gladman believe that the Council need to have a clear understanding of the level of residential development to be brought forward in the plan period when preparing the charging schedule as this will directly influence the scale of CIL that will be generated. Without this the charging schedule will not reflect the relevant and true infrastructure needs of the area.
Comment
Community Infrastructure Levy (CIL) Preliminary Draft Charging Schedule and Regulation 123 List
Q4. Do you agree with the proposed CIL charge rates for residential uses?
Representation ID: 21727
Received: 25/09/2014
Respondent: Gladman Developments
The CLG guidance notes that the use of differential rates can be an appropriate approach where evidence is clear. The regulations allow the application of differential rates, to ensure viability.
The rules are clear: they can only be applied in relation to different geographical zones in which development would be situated, related to different types of development, and/or scales of development. Charging schedules with differential rates should not have a disproportionate impact on particular sectors/specialist forms of development.
It is integral when setting differential rates for different areas that these rates are based on accurate, up-to-date housing market intelligence.
Introduction
Gladman Developments has considerable experience in the development industry in a number of sectors including residential and employment land. Gladman are aware that Rother Council have a Local Plan which has recently been found sound (subject to modifications) and that alongside this the Council are in the process of preparing a Community Infrastructure Levy for the area. This Consultation is for the PDCS stage of the CIL.
CIL is intended to have a positive effect on development. The latest CLG guidance notes that "The levy is expected to have a positive economic effect on development across a local plan area. When deciding the levy rates, an appropriate balance must be struck between additional investment for infrastructure to support development and the potential economic effect on the viability of developments...This balance is at the centre of the charge setting process" (Section 2.2, CLG Guidance, 2014).
In accordance with the latest CIL Regulations, the Council is required to strike an appropriate balance between the desirability of funding from CIL and the potential effects (taken as a whole) of the imposition of CIL on the economic viability of development across the local authority area. The Council must consider the impact of CIL together with the policies contained in the Local Plan on
developments within the borough when deciding an appropriate CIL rate.
Setting the levy at the appropriate rate will be key to ensuring that development comes forward in your local authority area and subsequently that the Local Plan is implemented. These representations address some key areas that local planning authorities must consider when preparing their CIL charging schedule, drawing on recent guidance produced by the CLG.
Funding gap / evidence base
Local planning authorities need to be able to demonstrate the infrastructure need and subsequent funding gap and must ensure that the level of total CIL receipts that could be generated through the levy reflects these true needs and the proposals in the Local Plan. The CIL should not be used by Council's as a mechanism for creating an unrealistic 'wish list' of infrastructure projects in their area.
When establishing a funding gap that CIL receipts are intended to contribute towards filling, it is vital that the Council take account of every possible income stream. This has to include an accurate assessment of future New Homes Bonus and council tax and business rates receipts generated as a result of new developments allocated in the Local Plan, as well as central government funding streams. This should also include an assessment of statutory undertakers' asset management plans, as these companies will at some stage be upgrading their systems/facilities. This also needs to be taken account of when assessing the infrastructure requirements of the authority.
The Council need to have an up to date, robust evidence base that fully justifies the infrastructure needs based on the amount of development that is required. Information on these infrastructure needs should, wherever possible, be drawn directly from the infrastructure planning that underpins the Development Plan, as this should identify the quantum and type of infrastructure required to realise their local development needs. If the authority's infrastructure planning is weak or out of date then the Council should undertake an exercise to refresh this. If the evidence base is not complete, robust and up to date the charging schedule will be unsound and the local planning authority will have difficulty adequately demonstrating their funding gap and subsequent CIL requirements.
The CLG guidance notes that: "Charging authorities should be able to show and
explain how their proposed Community Infrastructure Levy rate or rates will contribute towards the implementation of the relevant Plan, and support development across their area. Charging authorities will need to summarise their economic viability evidence. This evidence should be presented in a document (separate from the charging schedule) that shows the potential effects of the proposed levy rate or rates on the economic viability of development across the authority area" (Section 2:2:2:3, CLG Guidance, 2014).
It is important that in calculating the level of infrastructure the authority needs as a result of development the Council distinguishes between new and existing demands. New houses do not always create new pressure on infrastructure as evidence shows that a large proportion will be occupied by people already living in the borough, attending local schools, and registered with local GP surgeries. They will therefore require less infrastructure provision compared to new residents in the borough.
The available guidance makes it clear that CIL is expected to have a positive economic effect on development across an area in the medium to long term. As outlined in recent Inspector's Letters to East Devon District Council (April 2014), the CIL charging rates should not be set at such a level that would threaten development, and must be based on robust evidence and assumptions. The rate will also need to be appropriate over time, bearing in mind land values, market conditions and the wider economic climate change rapidly. The viability impact of incremental policy obligations, such as stepped Code for Sustainable Homes targets, must be assessed and reflected in the charging schedule.
The Council needs to ensure that they have a full understanding of the potential costs of infrastructure projects needed to meet the infrastructure needs. Gladman believe that it is inappropriate to set the levy based on a partial understanding of these infrastructure costs and in particular if the total money needed for infrastructure is unknown.
Differential charging rates
The CLG guidance notes that the use of differential charging rates can be an appropriate approach where there is clear viability evidence to justify this. The CIL regulations allow charging authorities to apply differential rates in a flexible way, to help ensure the viability of development is not put at risk.
The rules around the use of differential rates in the Charging Schedule are clear: they can only be applied in relation to different geographical zones in which development would be situated, related to different types of development, and/or scales of development. Furthermore as the Government's CIL guidance and inspectors have made clear, differential rates should be set "based on economic viability considerations alone, rather than any planning or any other public policy related choices" (Paragraph 14, Newark and Sherwood EIP report, August 2011), and "CIL is not intended to be a planning policy tool" (Paragraph 23, Huntingdonshire EIP report, April 2012). Charging schedules with differential rates should not have a disproportionate impact on particular sectors or specialist forms of development.
It is integral when setting differential rates for different geographical areas that these differential rates are based on accurate, up to date housing market intelligence forming the evidence base for this decision.
Discretionary Relief
Regulation 55 of the CIL Regulations allows local authorities to grant relief for exceptional circumstances from liability to pay CIL. Such provision should be factored into the Council's CIL and will avoid rendering sites with specific and exceptional cost burdens unviable should exceptional circumstances arise.
Payments in Kind
Regulations 73 and 73A of the CIL Regulations provides a mechanism for local authorities to accept infrastructure payments, or payments in kind, for land or infrastructure to be provided instead of money to satisfy a charge arising the levy. An allowance for infrastructure payments should therefore be made available by the Council, recognising that there may be time, cost and efficiency benefits in accepting land or infrastructure from parties liable for payment of the levy.
Requirement to consult
As with Local Plans, local planning authorities have an obligation to consult at various stages of the CIL preparation process. However, the guidance does not provide details as to the format that this consultation must take or length of the consultation period. Gladman echo the CIL guidance and would urge your local authority to engage with local developers and others in the property industry early and throughout the process. This will help your authority to gain opinions from the market to feed into the preparatory work.
Once the charging schedule is ready for Examination the local authority must publish the draft schedule for a further stage of formal public consultation. In accordance with the CIL Guidance this must be for a period of at least four weeks, although it is considered good practice to allow at least six weeks, and longer if the issues under consideration are particularly complex.
Examination
As outlined in Section 2:2:5:1 of the 2014 CLG guidance the charging authority must appoint the examiner. The examiner must be independent and have the appropriate qualifications and experience. The guidance confirms that a Planning Inspector would fulfil these criteria.
Conformity with the National Planning Policy Framework (NPPF)
The NPPF provides the current central government planning policy and requirements for local planning authorities to meet. The NPPF places emphasis on sustainable development and in particular ensuring that the objectively assessed needs of an area are met through the requirements and policies within the new Local Plan.
It is fundamental that the Council ensures that the proposed levy rates are realistic and not set too high. Arbitrarily high rates may jeopardise the delivery of housing schemes within the area. This would be contrary to the Government's aim outlined in the Framework to "significantly boost the supply of housing", as schemes may not come forward due to viability issues.
The Council's CIL charging rates must not threaten the overall delivery of the Local Plan, by making sites unviable. This point is reiterated in the CLG guidance, which states that "Charging authorities should set a rate which does not threaten the ability to develop viably the sites and scale of development identified in the relevant Plan" (Section 2:2, CLG Guidance, 2014).When testing the impact of CIL it is vital that the assumptions that underlie the standard residual valuation approach used to test the impact on viability of CIL are realistic and accurate.
This should include abnormal costs, contingency costs, preliminary costs, and developer profit, which should reflect the current level of risk perceived in the market.
Gladman would urge the Council to adopt an instalments policy for CIL payments as this will give developers the flexibility to pay contributions in line with development phasing schemes and will facilitate cash flow and therefore development viability. With this in mind, in accordance with Regulation 8(3A) of the CIL Regulations the Council should also accept the phasing of planning permissions, with each phase treated as a separate chargeable development.
Gladman also remind the Council of the need to review CIL tariffs once these have been set. The economic climate will inevitably change over the course of the plan period and as such the levy rates that can be set whilst ensuring development remains viable will also change. In accordance with the CLG guidance "Charging authorities must keep their charging schedules under review and should ensure that levy charges remain appropriate over time. For example charging schedules should take account of changes in market conditions, and remain relevant to the funding gap for the infrastructure needed to support the development of the area" (Section 2:2:6:3, CLG Guidance, 2014).
Gladman believe that the Council need to have a clear understanding of the level of residential development to be brought forward in the plan period when preparing the charging schedule as this will directly influence the scale of CIL that will be generated. Without this the charging schedule will not reflect the relevant and true infrastructure needs of the area.
Comment
Community Infrastructure Levy (CIL) Preliminary Draft Charging Schedule and Regulation 123 List
Q5. Do you agree with the proposed CIL rates for non-residential development?
Representation ID: 21728
Received: 25/09/2014
Respondent: Gladman Developments
The CLG guidance notes that the use of differential rates can be an appropriate approach where evidence is clear. The regulations allow the application of differential rates, to ensure viability.
The rules are clear: they can only be applied in relation to different geographical zones in which development would be situated, related to different types of development, and/or scales of development. Charging schedules with differential rates should not have a disproportionate impact on particular sectors/specialist forms of development.
It is integral when setting differential rates for different areas that these rates are based on accurate, up-to-date housing market intelligence.
Introduction
Gladman Developments has considerable experience in the development industry in a number of sectors including residential and employment land. Gladman are aware that Rother Council have a Local Plan which has recently been found sound (subject to modifications) and that alongside this the Council are in the process of preparing a Community Infrastructure Levy for the area. This Consultation is for the PDCS stage of the CIL.
CIL is intended to have a positive effect on development. The latest CLG guidance notes that "The levy is expected to have a positive economic effect on development across a local plan area. When deciding the levy rates, an appropriate balance must be struck between additional investment for infrastructure to support development and the potential economic effect on the viability of developments...This balance is at the centre of the charge setting process" (Section 2.2, CLG Guidance, 2014).
In accordance with the latest CIL Regulations, the Council is required to strike an appropriate balance between the desirability of funding from CIL and the potential effects (taken as a whole) of the imposition of CIL on the economic viability of development across the local authority area. The Council must consider the impact of CIL together with the policies contained in the Local Plan on
developments within the borough when deciding an appropriate CIL rate.
Setting the levy at the appropriate rate will be key to ensuring that development comes forward in your local authority area and subsequently that the Local Plan is implemented. These representations address some key areas that local planning authorities must consider when preparing their CIL charging schedule, drawing on recent guidance produced by the CLG.
Funding gap / evidence base
Local planning authorities need to be able to demonstrate the infrastructure need and subsequent funding gap and must ensure that the level of total CIL receipts that could be generated through the levy reflects these true needs and the proposals in the Local Plan. The CIL should not be used by Council's as a mechanism for creating an unrealistic 'wish list' of infrastructure projects in their area.
When establishing a funding gap that CIL receipts are intended to contribute towards filling, it is vital that the Council take account of every possible income stream. This has to include an accurate assessment of future New Homes Bonus and council tax and business rates receipts generated as a result of new developments allocated in the Local Plan, as well as central government funding streams. This should also include an assessment of statutory undertakers' asset management plans, as these companies will at some stage be upgrading their systems/facilities. This also needs to be taken account of when assessing the infrastructure requirements of the authority.
The Council need to have an up to date, robust evidence base that fully justifies the infrastructure needs based on the amount of development that is required. Information on these infrastructure needs should, wherever possible, be drawn directly from the infrastructure planning that underpins the Development Plan, as this should identify the quantum and type of infrastructure required to realise their local development needs. If the authority's infrastructure planning is weak or out of date then the Council should undertake an exercise to refresh this. If the evidence base is not complete, robust and up to date the charging schedule will be unsound and the local planning authority will have difficulty adequately demonstrating their funding gap and subsequent CIL requirements.
The CLG guidance notes that: "Charging authorities should be able to show and
explain how their proposed Community Infrastructure Levy rate or rates will contribute towards the implementation of the relevant Plan, and support development across their area. Charging authorities will need to summarise their economic viability evidence. This evidence should be presented in a document (separate from the charging schedule) that shows the potential effects of the proposed levy rate or rates on the economic viability of development across the authority area" (Section 2:2:2:3, CLG Guidance, 2014).
It is important that in calculating the level of infrastructure the authority needs as a result of development the Council distinguishes between new and existing demands. New houses do not always create new pressure on infrastructure as evidence shows that a large proportion will be occupied by people already living in the borough, attending local schools, and registered with local GP surgeries. They will therefore require less infrastructure provision compared to new residents in the borough.
The available guidance makes it clear that CIL is expected to have a positive economic effect on development across an area in the medium to long term. As outlined in recent Inspector's Letters to East Devon District Council (April 2014), the CIL charging rates should not be set at such a level that would threaten development, and must be based on robust evidence and assumptions. The rate will also need to be appropriate over time, bearing in mind land values, market conditions and the wider economic climate change rapidly. The viability impact of incremental policy obligations, such as stepped Code for Sustainable Homes targets, must be assessed and reflected in the charging schedule.
The Council needs to ensure that they have a full understanding of the potential costs of infrastructure projects needed to meet the infrastructure needs. Gladman believe that it is inappropriate to set the levy based on a partial understanding of these infrastructure costs and in particular if the total money needed for infrastructure is unknown.
Differential charging rates
The CLG guidance notes that the use of differential charging rates can be an appropriate approach where there is clear viability evidence to justify this. The CIL regulations allow charging authorities to apply differential rates in a flexible way, to help ensure the viability of development is not put at risk.
The rules around the use of differential rates in the Charging Schedule are clear: they can only be applied in relation to different geographical zones in which development would be situated, related to different types of development, and/or scales of development. Furthermore as the Government's CIL guidance and inspectors have made clear, differential rates should be set "based on economic viability considerations alone, rather than any planning or any other public policy related choices" (Paragraph 14, Newark and Sherwood EIP report, August 2011), and "CIL is not intended to be a planning policy tool" (Paragraph 23, Huntingdonshire EIP report, April 2012). Charging schedules with differential rates should not have a disproportionate impact on particular sectors or specialist forms of development.
It is integral when setting differential rates for different geographical areas that these differential rates are based on accurate, up to date housing market intelligence forming the evidence base for this decision.
Discretionary Relief
Regulation 55 of the CIL Regulations allows local authorities to grant relief for exceptional circumstances from liability to pay CIL. Such provision should be factored into the Council's CIL and will avoid rendering sites with specific and exceptional cost burdens unviable should exceptional circumstances arise.
Payments in Kind
Regulations 73 and 73A of the CIL Regulations provides a mechanism for local authorities to accept infrastructure payments, or payments in kind, for land or infrastructure to be provided instead of money to satisfy a charge arising the levy. An allowance for infrastructure payments should therefore be made available by the Council, recognising that there may be time, cost and efficiency benefits in accepting land or infrastructure from parties liable for payment of the levy.
Requirement to consult
As with Local Plans, local planning authorities have an obligation to consult at various stages of the CIL preparation process. However, the guidance does not provide details as to the format that this consultation must take or length of the consultation period. Gladman echo the CIL guidance and would urge your local authority to engage with local developers and others in the property industry early and throughout the process. This will help your authority to gain opinions from the market to feed into the preparatory work.
Once the charging schedule is ready for Examination the local authority must publish the draft schedule for a further stage of formal public consultation. In accordance with the CIL Guidance this must be for a period of at least four weeks, although it is considered good practice to allow at least six weeks, and longer if the issues under consideration are particularly complex.
Examination
As outlined in Section 2:2:5:1 of the 2014 CLG guidance the charging authority must appoint the examiner. The examiner must be independent and have the appropriate qualifications and experience. The guidance confirms that a Planning Inspector would fulfil these criteria.
Conformity with the National Planning Policy Framework (NPPF)
The NPPF provides the current central government planning policy and requirements for local planning authorities to meet. The NPPF places emphasis on sustainable development and in particular ensuring that the objectively assessed needs of an area are met through the requirements and policies within the new Local Plan.
It is fundamental that the Council ensures that the proposed levy rates are realistic and not set too high. Arbitrarily high rates may jeopardise the delivery of housing schemes within the area. This would be contrary to the Government's aim outlined in the Framework to "significantly boost the supply of housing", as schemes may not come forward due to viability issues.
The Council's CIL charging rates must not threaten the overall delivery of the Local Plan, by making sites unviable. This point is reiterated in the CLG guidance, which states that "Charging authorities should set a rate which does not threaten the ability to develop viably the sites and scale of development identified in the relevant Plan" (Section 2:2, CLG Guidance, 2014).When testing the impact of CIL it is vital that the assumptions that underlie the standard residual valuation approach used to test the impact on viability of CIL are realistic and accurate.
This should include abnormal costs, contingency costs, preliminary costs, and developer profit, which should reflect the current level of risk perceived in the market.
Gladman would urge the Council to adopt an instalments policy for CIL payments as this will give developers the flexibility to pay contributions in line with development phasing schemes and will facilitate cash flow and therefore development viability. With this in mind, in accordance with Regulation 8(3A) of the CIL Regulations the Council should also accept the phasing of planning permissions, with each phase treated as a separate chargeable development.
Gladman also remind the Council of the need to review CIL tariffs once these have been set. The economic climate will inevitably change over the course of the plan period and as such the levy rates that can be set whilst ensuring development remains viable will also change. In accordance with the CLG guidance "Charging authorities must keep their charging schedules under review and should ensure that levy charges remain appropriate over time. For example charging schedules should take account of changes in market conditions, and remain relevant to the funding gap for the infrastructure needed to support the development of the area" (Section 2:2:6:3, CLG Guidance, 2014).
Gladman believe that the Council need to have a clear understanding of the level of residential development to be brought forward in the plan period when preparing the charging schedule as this will directly influence the scale of CIL that will be generated. Without this the charging schedule will not reflect the relevant and true infrastructure needs of the area.
Comment
Community Infrastructure Levy (CIL) Preliminary Draft Charging Schedule and Regulation 123 List
Q7. Do you have any views on whether the District Council should introduce a discretionary and exceptional relief policy?
Representation ID: 21729
Received: 25/09/2014
Respondent: Gladman Developments
Discretionary Relief
Regulation 55 of the CIL Regulations allows local authorities to grant relief for exceptional circumstances from liability to pay CIL. Such provision should be factored into the Council's CIL and will avoid rendering sites with specific and exceptional cost burdens unviable should exceptional circumstances arise.
Introduction
Gladman Developments has considerable experience in the development industry in a number of sectors including residential and employment land. Gladman are aware that Rother Council have a Local Plan which has recently been found sound (subject to modifications) and that alongside this the Council are in the process of preparing a Community Infrastructure Levy for the area. This Consultation is for the PDCS stage of the CIL.
CIL is intended to have a positive effect on development. The latest CLG guidance notes that "The levy is expected to have a positive economic effect on development across a local plan area. When deciding the levy rates, an appropriate balance must be struck between additional investment for infrastructure to support development and the potential economic effect on the viability of developments...This balance is at the centre of the charge setting process" (Section 2.2, CLG Guidance, 2014).
In accordance with the latest CIL Regulations, the Council is required to strike an appropriate balance between the desirability of funding from CIL and the potential effects (taken as a whole) of the imposition of CIL on the economic viability of development across the local authority area. The Council must consider the impact of CIL together with the policies contained in the Local Plan on
developments within the borough when deciding an appropriate CIL rate.
Setting the levy at the appropriate rate will be key to ensuring that development comes forward in your local authority area and subsequently that the Local Plan is implemented. These representations address some key areas that local planning authorities must consider when preparing their CIL charging schedule, drawing on recent guidance produced by the CLG.
Funding gap / evidence base
Local planning authorities need to be able to demonstrate the infrastructure need and subsequent funding gap and must ensure that the level of total CIL receipts that could be generated through the levy reflects these true needs and the proposals in the Local Plan. The CIL should not be used by Council's as a mechanism for creating an unrealistic 'wish list' of infrastructure projects in their area.
When establishing a funding gap that CIL receipts are intended to contribute towards filling, it is vital that the Council take account of every possible income stream. This has to include an accurate assessment of future New Homes Bonus and council tax and business rates receipts generated as a result of new developments allocated in the Local Plan, as well as central government funding streams. This should also include an assessment of statutory undertakers' asset management plans, as these companies will at some stage be upgrading their systems/facilities. This also needs to be taken account of when assessing the infrastructure requirements of the authority.
The Council need to have an up to date, robust evidence base that fully justifies the infrastructure needs based on the amount of development that is required. Information on these infrastructure needs should, wherever possible, be drawn directly from the infrastructure planning that underpins the Development Plan, as this should identify the quantum and type of infrastructure required to realise their local development needs. If the authority's infrastructure planning is weak or out of date then the Council should undertake an exercise to refresh this. If the evidence base is not complete, robust and up to date the charging schedule will be unsound and the local planning authority will have difficulty adequately demonstrating their funding gap and subsequent CIL requirements.
The CLG guidance notes that: "Charging authorities should be able to show and
explain how their proposed Community Infrastructure Levy rate or rates will contribute towards the implementation of the relevant Plan, and support development across their area. Charging authorities will need to summarise their economic viability evidence. This evidence should be presented in a document (separate from the charging schedule) that shows the potential effects of the proposed levy rate or rates on the economic viability of development across the authority area" (Section 2:2:2:3, CLG Guidance, 2014).
It is important that in calculating the level of infrastructure the authority needs as a result of development the Council distinguishes between new and existing demands. New houses do not always create new pressure on infrastructure as evidence shows that a large proportion will be occupied by people already living in the borough, attending local schools, and registered with local GP surgeries. They will therefore require less infrastructure provision compared to new residents in the borough.
The available guidance makes it clear that CIL is expected to have a positive economic effect on development across an area in the medium to long term. As outlined in recent Inspector's Letters to East Devon District Council (April 2014), the CIL charging rates should not be set at such a level that would threaten development, and must be based on robust evidence and assumptions. The rate will also need to be appropriate over time, bearing in mind land values, market conditions and the wider economic climate change rapidly. The viability impact of incremental policy obligations, such as stepped Code for Sustainable Homes targets, must be assessed and reflected in the charging schedule.
The Council needs to ensure that they have a full understanding of the potential costs of infrastructure projects needed to meet the infrastructure needs. Gladman believe that it is inappropriate to set the levy based on a partial understanding of these infrastructure costs and in particular if the total money needed for infrastructure is unknown.
Differential charging rates
The CLG guidance notes that the use of differential charging rates can be an appropriate approach where there is clear viability evidence to justify this. The CIL regulations allow charging authorities to apply differential rates in a flexible way, to help ensure the viability of development is not put at risk.
The rules around the use of differential rates in the Charging Schedule are clear: they can only be applied in relation to different geographical zones in which development would be situated, related to different types of development, and/or scales of development. Furthermore as the Government's CIL guidance and inspectors have made clear, differential rates should be set "based on economic viability considerations alone, rather than any planning or any other public policy related choices" (Paragraph 14, Newark and Sherwood EIP report, August 2011), and "CIL is not intended to be a planning policy tool" (Paragraph 23, Huntingdonshire EIP report, April 2012). Charging schedules with differential rates should not have a disproportionate impact on particular sectors or specialist forms of development.
It is integral when setting differential rates for different geographical areas that these differential rates are based on accurate, up to date housing market intelligence forming the evidence base for this decision.
Discretionary Relief
Regulation 55 of the CIL Regulations allows local authorities to grant relief for exceptional circumstances from liability to pay CIL. Such provision should be factored into the Council's CIL and will avoid rendering sites with specific and exceptional cost burdens unviable should exceptional circumstances arise.
Payments in Kind
Regulations 73 and 73A of the CIL Regulations provides a mechanism for local authorities to accept infrastructure payments, or payments in kind, for land or infrastructure to be provided instead of money to satisfy a charge arising the levy. An allowance for infrastructure payments should therefore be made available by the Council, recognising that there may be time, cost and efficiency benefits in accepting land or infrastructure from parties liable for payment of the levy.
Requirement to consult
As with Local Plans, local planning authorities have an obligation to consult at various stages of the CIL preparation process. However, the guidance does not provide details as to the format that this consultation must take or length of the consultation period. Gladman echo the CIL guidance and would urge your local authority to engage with local developers and others in the property industry early and throughout the process. This will help your authority to gain opinions from the market to feed into the preparatory work.
Once the charging schedule is ready for Examination the local authority must publish the draft schedule for a further stage of formal public consultation. In accordance with the CIL Guidance this must be for a period of at least four weeks, although it is considered good practice to allow at least six weeks, and longer if the issues under consideration are particularly complex.
Examination
As outlined in Section 2:2:5:1 of the 2014 CLG guidance the charging authority must appoint the examiner. The examiner must be independent and have the appropriate qualifications and experience. The guidance confirms that a Planning Inspector would fulfil these criteria.
Conformity with the National Planning Policy Framework (NPPF)
The NPPF provides the current central government planning policy and requirements for local planning authorities to meet. The NPPF places emphasis on sustainable development and in particular ensuring that the objectively assessed needs of an area are met through the requirements and policies within the new Local Plan.
It is fundamental that the Council ensures that the proposed levy rates are realistic and not set too high. Arbitrarily high rates may jeopardise the delivery of housing schemes within the area. This would be contrary to the Government's aim outlined in the Framework to "significantly boost the supply of housing", as schemes may not come forward due to viability issues.
The Council's CIL charging rates must not threaten the overall delivery of the Local Plan, by making sites unviable. This point is reiterated in the CLG guidance, which states that "Charging authorities should set a rate which does not threaten the ability to develop viably the sites and scale of development identified in the relevant Plan" (Section 2:2, CLG Guidance, 2014).When testing the impact of CIL it is vital that the assumptions that underlie the standard residual valuation approach used to test the impact on viability of CIL are realistic and accurate.
This should include abnormal costs, contingency costs, preliminary costs, and developer profit, which should reflect the current level of risk perceived in the market.
Gladman would urge the Council to adopt an instalments policy for CIL payments as this will give developers the flexibility to pay contributions in line with development phasing schemes and will facilitate cash flow and therefore development viability. With this in mind, in accordance with Regulation 8(3A) of the CIL Regulations the Council should also accept the phasing of planning permissions, with each phase treated as a separate chargeable development.
Gladman also remind the Council of the need to review CIL tariffs once these have been set. The economic climate will inevitably change over the course of the plan period and as such the levy rates that can be set whilst ensuring development remains viable will also change. In accordance with the CLG guidance "Charging authorities must keep their charging schedules under review and should ensure that levy charges remain appropriate over time. For example charging schedules should take account of changes in market conditions, and remain relevant to the funding gap for the infrastructure needed to support the development of the area" (Section 2:2:6:3, CLG Guidance, 2014).
Gladman believe that the Council need to have a clear understanding of the level of residential development to be brought forward in the plan period when preparing the charging schedule as this will directly influence the scale of CIL that will be generated. Without this the charging schedule will not reflect the relevant and true infrastructure needs of the area.
Comment
Community Infrastructure Levy (CIL) Preliminary Draft Charging Schedule and Regulation 123 List
Q7. Do you have any views on whether the District Council should introduce a discretionary and exceptional relief policy?
Representation ID: 21730
Received: 25/09/2014
Respondent: Gladman Developments
Regulation 55 of the CIL Regulations allows local authorities to grant relief for exceptional circumstances from liability to pay CIL. Such provision should be factored into the Council's CIL and will avoid rendering sites with specific and exceptional cost burdens unviable should exceptional circumstances arise.
Introduction
Gladman Developments has considerable experience in the development industry in a number of sectors including residential and employment land. Gladman are aware that Rother Council have a Local Plan which has recently been found sound (subject to modifications) and that alongside this the Council are in the process of preparing a Community Infrastructure Levy for the area. This Consultation is for the PDCS stage of the CIL.
CIL is intended to have a positive effect on development. The latest CLG guidance notes that "The levy is expected to have a positive economic effect on development across a local plan area. When deciding the levy rates, an appropriate balance must be struck between additional investment for infrastructure to support development and the potential economic effect on the viability of developments...This balance is at the centre of the charge setting process" (Section 2.2, CLG Guidance, 2014).
In accordance with the latest CIL Regulations, the Council is required to strike an appropriate balance between the desirability of funding from CIL and the potential effects (taken as a whole) of the imposition of CIL on the economic viability of development across the local authority area. The Council must consider the impact of CIL together with the policies contained in the Local Plan on
developments within the borough when deciding an appropriate CIL rate.
Setting the levy at the appropriate rate will be key to ensuring that development comes forward in your local authority area and subsequently that the Local Plan is implemented. These representations address some key areas that local planning authorities must consider when preparing their CIL charging schedule, drawing on recent guidance produced by the CLG.
Funding gap / evidence base
Local planning authorities need to be able to demonstrate the infrastructure need and subsequent funding gap and must ensure that the level of total CIL receipts that could be generated through the levy reflects these true needs and the proposals in the Local Plan. The CIL should not be used by Council's as a mechanism for creating an unrealistic 'wish list' of infrastructure projects in their area.
When establishing a funding gap that CIL receipts are intended to contribute towards filling, it is vital that the Council take account of every possible income stream. This has to include an accurate assessment of future New Homes Bonus and council tax and business rates receipts generated as a result of new developments allocated in the Local Plan, as well as central government funding streams. This should also include an assessment of statutory undertakers' asset management plans, as these companies will at some stage be upgrading their systems/facilities. This also needs to be taken account of when assessing the infrastructure requirements of the authority.
The Council need to have an up to date, robust evidence base that fully justifies the infrastructure needs based on the amount of development that is required. Information on these infrastructure needs should, wherever possible, be drawn directly from the infrastructure planning that underpins the Development Plan, as this should identify the quantum and type of infrastructure required to realise their local development needs. If the authority's infrastructure planning is weak or out of date then the Council should undertake an exercise to refresh this. If the evidence base is not complete, robust and up to date the charging schedule will be unsound and the local planning authority will have difficulty adequately demonstrating their funding gap and subsequent CIL requirements.
The CLG guidance notes that: "Charging authorities should be able to show and
explain how their proposed Community Infrastructure Levy rate or rates will contribute towards the implementation of the relevant Plan, and support development across their area. Charging authorities will need to summarise their economic viability evidence. This evidence should be presented in a document (separate from the charging schedule) that shows the potential effects of the proposed levy rate or rates on the economic viability of development across the authority area" (Section 2:2:2:3, CLG Guidance, 2014).
It is important that in calculating the level of infrastructure the authority needs as a result of development the Council distinguishes between new and existing demands. New houses do not always create new pressure on infrastructure as evidence shows that a large proportion will be occupied by people already living in the borough, attending local schools, and registered with local GP surgeries. They will therefore require less infrastructure provision compared to new residents in the borough.
The available guidance makes it clear that CIL is expected to have a positive economic effect on development across an area in the medium to long term. As outlined in recent Inspector's Letters to East Devon District Council (April 2014), the CIL charging rates should not be set at such a level that would threaten development, and must be based on robust evidence and assumptions. The rate will also need to be appropriate over time, bearing in mind land values, market conditions and the wider economic climate change rapidly. The viability impact of incremental policy obligations, such as stepped Code for Sustainable Homes targets, must be assessed and reflected in the charging schedule.
The Council needs to ensure that they have a full understanding of the potential costs of infrastructure projects needed to meet the infrastructure needs. Gladman believe that it is inappropriate to set the levy based on a partial understanding of these infrastructure costs and in particular if the total money needed for infrastructure is unknown.
Differential charging rates
The CLG guidance notes that the use of differential charging rates can be an appropriate approach where there is clear viability evidence to justify this. The CIL regulations allow charging authorities to apply differential rates in a flexible way, to help ensure the viability of development is not put at risk.
The rules around the use of differential rates in the Charging Schedule are clear: they can only be applied in relation to different geographical zones in which development would be situated, related to different types of development, and/or scales of development. Furthermore as the Government's CIL guidance and inspectors have made clear, differential rates should be set "based on economic viability considerations alone, rather than any planning or any other public policy related choices" (Paragraph 14, Newark and Sherwood EIP report, August 2011), and "CIL is not intended to be a planning policy tool" (Paragraph 23, Huntingdonshire EIP report, April 2012). Charging schedules with differential rates should not have a disproportionate impact on particular sectors or specialist forms of development.
It is integral when setting differential rates for different geographical areas that these differential rates are based on accurate, up to date housing market intelligence forming the evidence base for this decision.
Discretionary Relief
Regulation 55 of the CIL Regulations allows local authorities to grant relief for exceptional circumstances from liability to pay CIL. Such provision should be factored into the Council's CIL and will avoid rendering sites with specific and exceptional cost burdens unviable should exceptional circumstances arise.
Payments in Kind
Regulations 73 and 73A of the CIL Regulations provides a mechanism for local authorities to accept infrastructure payments, or payments in kind, for land or infrastructure to be provided instead of money to satisfy a charge arising the levy. An allowance for infrastructure payments should therefore be made available by the Council, recognising that there may be time, cost and efficiency benefits in accepting land or infrastructure from parties liable for payment of the levy.
Requirement to consult
As with Local Plans, local planning authorities have an obligation to consult at various stages of the CIL preparation process. However, the guidance does not provide details as to the format that this consultation must take or length of the consultation period. Gladman echo the CIL guidance and would urge your local authority to engage with local developers and others in the property industry early and throughout the process. This will help your authority to gain opinions from the market to feed into the preparatory work.
Once the charging schedule is ready for Examination the local authority must publish the draft schedule for a further stage of formal public consultation. In accordance with the CIL Guidance this must be for a period of at least four weeks, although it is considered good practice to allow at least six weeks, and longer if the issues under consideration are particularly complex.
Examination
As outlined in Section 2:2:5:1 of the 2014 CLG guidance the charging authority must appoint the examiner. The examiner must be independent and have the appropriate qualifications and experience. The guidance confirms that a Planning Inspector would fulfil these criteria.
Conformity with the National Planning Policy Framework (NPPF)
The NPPF provides the current central government planning policy and requirements for local planning authorities to meet. The NPPF places emphasis on sustainable development and in particular ensuring that the objectively assessed needs of an area are met through the requirements and policies within the new Local Plan.
It is fundamental that the Council ensures that the proposed levy rates are realistic and not set too high. Arbitrarily high rates may jeopardise the delivery of housing schemes within the area. This would be contrary to the Government's aim outlined in the Framework to "significantly boost the supply of housing", as schemes may not come forward due to viability issues.
The Council's CIL charging rates must not threaten the overall delivery of the Local Plan, by making sites unviable. This point is reiterated in the CLG guidance, which states that "Charging authorities should set a rate which does not threaten the ability to develop viably the sites and scale of development identified in the relevant Plan" (Section 2:2, CLG Guidance, 2014).When testing the impact of CIL it is vital that the assumptions that underlie the standard residual valuation approach used to test the impact on viability of CIL are realistic and accurate.
This should include abnormal costs, contingency costs, preliminary costs, and developer profit, which should reflect the current level of risk perceived in the market.
Gladman would urge the Council to adopt an instalments policy for CIL payments as this will give developers the flexibility to pay contributions in line with development phasing schemes and will facilitate cash flow and therefore development viability. With this in mind, in accordance with Regulation 8(3A) of the CIL Regulations the Council should also accept the phasing of planning permissions, with each phase treated as a separate chargeable development.
Gladman also remind the Council of the need to review CIL tariffs once these have been set. The economic climate will inevitably change over the course of the plan period and as such the levy rates that can be set whilst ensuring development remains viable will also change. In accordance with the CLG guidance "Charging authorities must keep their charging schedules under review and should ensure that levy charges remain appropriate over time. For example charging schedules should take account of changes in market conditions, and remain relevant to the funding gap for the infrastructure needed to support the development of the area" (Section 2:2:6:3, CLG Guidance, 2014).
Gladman believe that the Council need to have a clear understanding of the level of residential development to be brought forward in the plan period when preparing the charging schedule as this will directly influence the scale of CIL that will be generated. Without this the charging schedule will not reflect the relevant and true infrastructure needs of the area.
Comment
Community Infrastructure Levy (CIL) Preliminary Draft Charging Schedule and Regulation 123 List
Q9. Do you have any further comments on the PDCS?
Representation ID: 21731
Received: 25/09/2014
Respondent: Gladman Developments
Gladman urge the Council to adopt an instalments policy for CIL payments as this will give developers the flexibility to pay contributions in line with development phasing and facilitate cash flow and therefore viability.
Gladman also remind the Council of the need to review CIL tariffs once these have been set.
Gladman believe that the Council need to have a clear understanding of the level of development to be brought forward in the plan when preparing the charging schedule as this will directly influence the scale of CIL. Without this the charging schedule will not reflect the relevant/true infrastructure needs.
Introduction
Gladman Developments has considerable experience in the development industry in a number of sectors including residential and employment land. Gladman are aware that Rother Council have a Local Plan which has recently been found sound (subject to modifications) and that alongside this the Council are in the process of preparing a Community Infrastructure Levy for the area. This Consultation is for the PDCS stage of the CIL.
CIL is intended to have a positive effect on development. The latest CLG guidance notes that "The levy is expected to have a positive economic effect on development across a local plan area. When deciding the levy rates, an appropriate balance must be struck between additional investment for infrastructure to support development and the potential economic effect on the viability of developments...This balance is at the centre of the charge setting process" (Section 2.2, CLG Guidance, 2014).
In accordance with the latest CIL Regulations, the Council is required to strike an appropriate balance between the desirability of funding from CIL and the potential effects (taken as a whole) of the imposition of CIL on the economic viability of development across the local authority area. The Council must consider the impact of CIL together with the policies contained in the Local Plan on
developments within the borough when deciding an appropriate CIL rate.
Setting the levy at the appropriate rate will be key to ensuring that development comes forward in your local authority area and subsequently that the Local Plan is implemented. These representations address some key areas that local planning authorities must consider when preparing their CIL charging schedule, drawing on recent guidance produced by the CLG.
Funding gap / evidence base
Local planning authorities need to be able to demonstrate the infrastructure need and subsequent funding gap and must ensure that the level of total CIL receipts that could be generated through the levy reflects these true needs and the proposals in the Local Plan. The CIL should not be used by Council's as a mechanism for creating an unrealistic 'wish list' of infrastructure projects in their area.
When establishing a funding gap that CIL receipts are intended to contribute towards filling, it is vital that the Council take account of every possible income stream. This has to include an accurate assessment of future New Homes Bonus and council tax and business rates receipts generated as a result of new developments allocated in the Local Plan, as well as central government funding streams. This should also include an assessment of statutory undertakers' asset management plans, as these companies will at some stage be upgrading their systems/facilities. This also needs to be taken account of when assessing the infrastructure requirements of the authority.
The Council need to have an up to date, robust evidence base that fully justifies the infrastructure needs based on the amount of development that is required. Information on these infrastructure needs should, wherever possible, be drawn directly from the infrastructure planning that underpins the Development Plan, as this should identify the quantum and type of infrastructure required to realise their local development needs. If the authority's infrastructure planning is weak or out of date then the Council should undertake an exercise to refresh this. If the evidence base is not complete, robust and up to date the charging schedule will be unsound and the local planning authority will have difficulty adequately demonstrating their funding gap and subsequent CIL requirements.
The CLG guidance notes that: "Charging authorities should be able to show and
explain how their proposed Community Infrastructure Levy rate or rates will contribute towards the implementation of the relevant Plan, and support development across their area. Charging authorities will need to summarise their economic viability evidence. This evidence should be presented in a document (separate from the charging schedule) that shows the potential effects of the proposed levy rate or rates on the economic viability of development across the authority area" (Section 2:2:2:3, CLG Guidance, 2014).
It is important that in calculating the level of infrastructure the authority needs as a result of development the Council distinguishes between new and existing demands. New houses do not always create new pressure on infrastructure as evidence shows that a large proportion will be occupied by people already living in the borough, attending local schools, and registered with local GP surgeries. They will therefore require less infrastructure provision compared to new residents in the borough.
The available guidance makes it clear that CIL is expected to have a positive economic effect on development across an area in the medium to long term. As outlined in recent Inspector's Letters to East Devon District Council (April 2014), the CIL charging rates should not be set at such a level that would threaten development, and must be based on robust evidence and assumptions. The rate will also need to be appropriate over time, bearing in mind land values, market conditions and the wider economic climate change rapidly. The viability impact of incremental policy obligations, such as stepped Code for Sustainable Homes targets, must be assessed and reflected in the charging schedule.
The Council needs to ensure that they have a full understanding of the potential costs of infrastructure projects needed to meet the infrastructure needs. Gladman believe that it is inappropriate to set the levy based on a partial understanding of these infrastructure costs and in particular if the total money needed for infrastructure is unknown.
Differential charging rates
The CLG guidance notes that the use of differential charging rates can be an appropriate approach where there is clear viability evidence to justify this. The CIL regulations allow charging authorities to apply differential rates in a flexible way, to help ensure the viability of development is not put at risk.
The rules around the use of differential rates in the Charging Schedule are clear: they can only be applied in relation to different geographical zones in which development would be situated, related to different types of development, and/or scales of development. Furthermore as the Government's CIL guidance and inspectors have made clear, differential rates should be set "based on economic viability considerations alone, rather than any planning or any other public policy related choices" (Paragraph 14, Newark and Sherwood EIP report, August 2011), and "CIL is not intended to be a planning policy tool" (Paragraph 23, Huntingdonshire EIP report, April 2012). Charging schedules with differential rates should not have a disproportionate impact on particular sectors or specialist forms of development.
It is integral when setting differential rates for different geographical areas that these differential rates are based on accurate, up to date housing market intelligence forming the evidence base for this decision.
Discretionary Relief
Regulation 55 of the CIL Regulations allows local authorities to grant relief for exceptional circumstances from liability to pay CIL. Such provision should be factored into the Council's CIL and will avoid rendering sites with specific and exceptional cost burdens unviable should exceptional circumstances arise.
Payments in Kind
Regulations 73 and 73A of the CIL Regulations provides a mechanism for local authorities to accept infrastructure payments, or payments in kind, for land or infrastructure to be provided instead of money to satisfy a charge arising the levy. An allowance for infrastructure payments should therefore be made available by the Council, recognising that there may be time, cost and efficiency benefits in accepting land or infrastructure from parties liable for payment of the levy.
Requirement to consult
As with Local Plans, local planning authorities have an obligation to consult at various stages of the CIL preparation process. However, the guidance does not provide details as to the format that this consultation must take or length of the consultation period. Gladman echo the CIL guidance and would urge your local authority to engage with local developers and others in the property industry early and throughout the process. This will help your authority to gain opinions from the market to feed into the preparatory work.
Once the charging schedule is ready for Examination the local authority must publish the draft schedule for a further stage of formal public consultation. In accordance with the CIL Guidance this must be for a period of at least four weeks, although it is considered good practice to allow at least six weeks, and longer if the issues under consideration are particularly complex.
Examination
As outlined in Section 2:2:5:1 of the 2014 CLG guidance the charging authority must appoint the examiner. The examiner must be independent and have the appropriate qualifications and experience. The guidance confirms that a Planning Inspector would fulfil these criteria.
Conformity with the National Planning Policy Framework (NPPF)
The NPPF provides the current central government planning policy and requirements for local planning authorities to meet. The NPPF places emphasis on sustainable development and in particular ensuring that the objectively assessed needs of an area are met through the requirements and policies within the new Local Plan.
It is fundamental that the Council ensures that the proposed levy rates are realistic and not set too high. Arbitrarily high rates may jeopardise the delivery of housing schemes within the area. This would be contrary to the Government's aim outlined in the Framework to "significantly boost the supply of housing", as schemes may not come forward due to viability issues.
The Council's CIL charging rates must not threaten the overall delivery of the Local Plan, by making sites unviable. This point is reiterated in the CLG guidance, which states that "Charging authorities should set a rate which does not threaten the ability to develop viably the sites and scale of development identified in the relevant Plan" (Section 2:2, CLG Guidance, 2014).When testing the impact of CIL it is vital that the assumptions that underlie the standard residual valuation approach used to test the impact on viability of CIL are realistic and accurate.
This should include abnormal costs, contingency costs, preliminary costs, and developer profit, which should reflect the current level of risk perceived in the market.
Gladman would urge the Council to adopt an instalments policy for CIL payments as this will give developers the flexibility to pay contributions in line with development phasing schemes and will facilitate cash flow and therefore development viability. With this in mind, in accordance with Regulation 8(3A) of the CIL Regulations the Council should also accept the phasing of planning permissions, with each phase treated as a separate chargeable development.
Gladman also remind the Council of the need to review CIL tariffs once these have been set. The economic climate will inevitably change over the course of the plan period and as such the levy rates that can be set whilst ensuring development remains viable will also change. In accordance with the CLG guidance "Charging authorities must keep their charging schedules under review and should ensure that levy charges remain appropriate over time. For example charging schedules should take account of changes in market conditions, and remain relevant to the funding gap for the infrastructure needed to support the development of the area" (Section 2:2:6:3, CLG Guidance, 2014).
Gladman believe that the Council need to have a clear understanding of the level of residential development to be brought forward in the plan period when preparing the charging schedule as this will directly influence the scale of CIL that will be generated. Without this the charging schedule will not reflect the relevant and true infrastructure needs of the area.