Rother Local Plan 2025-2042 Regulation 19 (pre-submission) version September 2026
Search representations
Results for National Grid Electricity Transmission search
New searchSupport
Rother Local Plan 2025-2042 Regulation 19 (pre-submission) version September 2026
Policy INF1: Strategic Infrastructure Requirements
Representation ID: 31727
Received: 12/11/2026
Respondent: National Grid Electricity Transmission
Agent: Fisher German LLP
National Grid Electricity Transmission (NGET) owns and maintains the electricity transmission system in England and Wales, operating independently from National Grid Electricity Distribution (NGED), National Gas Transmission, National Grid Ventures (NGV), and the National Energy System Operator (NESO). Because NESO assumed electricity and gas network planning responsibilities on 1st October 2024, NGET recommends early engagement with NESO to establish available supply capacity and required reinforcement for potential development sites, alongside consulting NGED, NGV, and National Gas Transmission separately.
Support
Rother Local Plan 2025-2042 Regulation 19 (pre-submission) version September 2026
Policy INF1: Strategic Infrastructure Requirements
Representation ID: 31728
Received: 12/11/2026
Respondent: National Grid Electricity Transmission
Agent: Fisher German LLP
NGET has identified specific assets within the Plan area, including the 400kV Dungeness–Ninfield 1 & 2 and Bolney–Ninfield 2 overhead transmission lines, the Ninfield 400kV and 132kV substations, and freehold land at Ninfield. Although NGET generally does not own the land crossed by its overhead lines, increasing development pressure is bringing more sites forward near its assets. Despite not being a statutory consultee in the plan-making process, NGET recommends being consulted at the earliest possible opportunity so its advice is taken into account on policies or developments affecting electricity supply.
Support
Rother Local Plan 2025-2042 Regulation 19 (pre-submission) version September 2026
Policy INF1: Strategic Infrastructure Requirements
Representation ID: 31730
Received: 12/11/2026
Respondent: National Grid Electricity Transmission
Agent: Fisher German LLP
Because UK energy security and the net zero transition rely on a dependable electricity network, the Council should ensure proposals near transmission assets do not compromise safety, operability, maintenance access, asset replacement, or future expansion. Specifically, the Council should safeguard existing and potential access routes for Abnormal Indivisible Loads (AILs) required to deliver or remove large transmission equipment, such as transformers at strategic substations, and resist development or highway alterations that would prejudice, constrain, or render AIL access impractical unless suitable mitigation or agreed alternative routes are secured.
Support
Rother Local Plan 2025-2042 Regulation 19 (pre-submission) version September 2026
Policy INF1: Strategic Infrastructure Requirements
Representation ID: 31731
Received: 12/11/2026
Respondent: National Grid Electricity Transmission
Agent: Fisher German LLP
While there are currently no known New Infrastructure interactions in Rother, electricity demand will rise significantly to meet the UK Government's 2050 net zero commitment. NGET is evolving its network of overhead lines, pylons, and cables to accommodate low-carbon generation, offshore wind, and subsea interconnectors. In planning for the area, the Council should safeguard all existing transmission infrastructure, support future reinforcement and expansion—including works for the Great Grid Upgrade and strategic national infrastructure projects—and encourage early engagement with NGET to identify and resolve potential impacts early in the planning process.
Support
Rother Local Plan 2025-2042 Regulation 19 (pre-submission) version September 2026
Policy INF1: Strategic Infrastructure Requirements
Representation ID: 31732
Received: 12/11/2026
Respondent: National Grid Electricity Transmission
Agent: Fisher German LLP
NGET’s policy is to retain existing overhead lines in-situ barring exceptional circumstances of regional or national importance, promoting creative site design near pylons through its published design guidelines. Developments must not infringe statutory safety clearances between overhead lines, built structures, or altered ground levels, for which NGET can supply detailed line profile drawings. Decision-makers should also apply NGET’s guidance on substation operational noise alongside the NPPF’s 'Agent of Change' principle, and utilise Regen/DESNZ guidance when assessing electricity network infrastructure applications.
Support
Rother Local Plan 2025-2042 Regulation 19 (pre-submission) version September 2026
Policy INF1: Strategic Infrastructure Requirements
Representation ID: 31734
Received: 12/11/2026
Respondent: National Grid Electricity Transmission
Agent: Fisher German LLP
To ensure the continued safe operation of existing sites and facilitate future infrastructure investment, NGET wishes to be involved in the preparation, alteration, and review of plans and strategies affecting its assets. NGET offers confidential informal comments during policy development and requests to be consulted on any Development Plan Document (DPD) or site-specific proposals that could affect its network, asking the Council to add representatives from Fisher German LLP and NGET to its consultation database.